Demand for electricity is up in the United States, and so is its price. One way to increase supply and lower costs is to build new power plants, but that can take years and cost a fortune. Talgat Kopzhanov is working on a faster, more affordable solution: the generator replacement interconnection process.
The technique links renewable energy sources to the grid connections of shuttered or underutilized power facilities and coal plants. The process uses the existing interconnection rights and infrastructure when generating electricity, eliminating the years-long approval process for constructing new U.S. power facilities.
Talgat Kopzhanov
Employer
Middle River Power, in Chicago
Job title
Asset manager
Member grade
Senior member
Alma maters
Purdue University in West Lafayette, Ind., and Indiana University in Bloomington
Kopzhanov, an IEEE senior member, is an asset manager for Middle River Power, based in Chicago. The private equity–sponsored investment and asset management organization specializes in U.S. power generation assets.
“Every power plant has its own interconnection rights,” he says, “but, amazingly, most are not fully utilizing them.” Interconnection rights give a new power source—such as solar energy—permission to connect to a high-voltage transmission system.
“We build the new renewable energy resources on top of them,” Kopzhanov says. “It’s like colocating a new power plant.”
He recently oversaw the installation of two generator-replacement interconnection projects, one for a solar system in Minnesota and the other for a battery storage facility in California.
A fast-track approach that cuts costs
Artificial intelligence data centers are driving up demand and raising electricity bills globally. Although tech companies and investors are willing to spend trillions of U.S. dollars constructing new power facilities, it can take up to seven years just to secure the grid interconnection rights needed to start building a plant, Kopzhanov says. The lengthy process involves system planning, permit requests, and regulatory approvals. Only about 5 percent of new projects are approved each year, he says, in part because of grid reliability issues.
The interconnection technique takes about half the time, he says, bringing cleaner energy online faster. By overcoming interconnection bottlenecks, such as major transmission upgrades that delay renewable projects, the process speeds up project timelines and lowers expenses.
Kopzhanov explains the technique in an on-demand educational webinar, Unlocking Surplus Interconnection Service. Colocating Renewable and Thermal Power Plants, hosted by the IEEE Power & Energy Society. The webinar is available to the public for a fee.
Kopzhanov has been involved with several recent generator replacement interconnection installations. In May the Sherco Solar project in Sherburne County, Minn., replaced a retiring coal plant with…
Read full article: Power Grid Interconnections: A Renewable Energy Source
The post “Power Grid Interconnections: A Renewable Energy Source” by Kathy Pretz was published on 12/19/2025 by spectrum.ieee.org